Project Details:
- LPG Storage Tank: Installation of 3.5-ton tanks, 2 units (total reserve capacity 7 tons), positioned according to advanced safety engineering principles
(Safety Distancing) - Vaporizer: Installation of high-efficiency 400 kg/hr vaporizers, 2 units, to support continuous and stable boiler operation.
- Piping System: Gas piping from the supply station to the boiler, using materials and welding standards verified by legally required pressure testing.
Standards and Safety
- Safety system: Installation of gas leak detection systems
(Gas Detector) - Engineering: Installation, testing, and supervision by specialist engineers.
- Regulatory standards: Designed and installed to Department of Energy Business standards and industrial factory safety requirements.
- Testing: The system undergoes high-pressure performance testing (Hydrostatic Test & Leak Test) before commissioning
for maximum confidence.